Continental Construction Management Constructed Gratiot Central Commons
As of March 2018, demolition and site work is complete, we are pouring the footings, and the masons are installing the block.
This is a new construction of a 52,000-square-foot, four-story building that will have 36 affordable housing units and ground-floor retail space facing the street.
The Gratiot Central Commons will be situated between two existing mixed-use buildings. The Detroit Catholic Pastoral Alliance owns 8900 Gratiot and 9200 Gratiot. This building will create a seamless stretch of storefronts along a commercial corridor challenged by decades of disinvestment and blight.
http://www.continentalmgt.com/
LOCATION/MAP:
9100 Gratiot Avenue, Detroit, MI 48213
TIMELINE:
2017 (Currently under construction as of March 2018—Expected to be completed in 14 months)
COST/FUNDING:
$5.89M / MSHDA Low Income Housing Tax Credits (Section 3)